Lahaina Wildfire
Debris Transfer Advisory
Dashboard

Rebuild Dashboard

UPDATED NOVEMBER 3, 2025

All Housing & Permitting Updates

Data provided by

341

Being Processed

Total Building Permits

185

Residential

156

Non-residential


Application for permit has been submitted and is being processed.

527

Issued

Total Building Permits

497

Residential

30

Non-residential


Permit has been issued, allowing for construction to begin.

85

Completed

Total Building Permits

81

Residential

4

Non-residential


Permit has been completed, with home having passed final inspection and ready for habitation.

295

In Construction

Total Homes under Construction

*Non-Residential includes commercial properties, properties with 4 or more dwelling units, and all Puamana permits.

UPDATED NOVEMBER 3, 2025

Lahaina Permitting Updates

Data provided by

340

Being Processed

Building Permits in Process

184

Residential

156

Non-residential


Application for permit has been submitted and is being processed

518

Issued

Building Permits Issued

488

Residential

30

Non-residential


Permit has been issued, but not yet completed.

80

Completed

Building Permits Completed

76

Residential

4

Non-residential


Permit has been completed, with home having passed final inspection and ready for habitation.

UPDATED NOVEMBER 3, 2025

Upcountry Permitting Updates

Data provided by

1

Being Processed

Building Permits in Process

1

Residential

0

Non-residential


Application for permit has been submitted and is being processed

9

Issued

Building Permits Issued

9

Residential

0

Non-residential


Permit has been issued, but not yet completed.

5

Completed

Building Permits Completed

5

Residential

0

Non-residential


Permit has been completed, with home having passed final inspection and ready for habitation.

UPDATED NOVEMBER 3, 2025
Phase 1

Debris Transfer Progress Complete

Completed

Started

Complete

Phase 2

TDS Restoration Tracker

Note: Trucks will continue to make trips between the TDS site and the PDS during restoration activities.

TDS infrastructure removed

Temporary traffic signals removed

Road alterations restored

Old Cane Haul Road restored

Sampling completed

Demobilization

Completed

Underway

To be completed

All Debris Removal Updates

Data provided by

Before

Debris Removal Front Street Pilings

After

Debris Removal Front Street Pilings

100% Complete

Kealamoka Fleming Road Sewer Line

Start Date: 10 JUL 24 (Awarded)
Anticipated Completion: 15 MAR 25

1500/1500 LF 8” sewer main installed
1000/1000 LF 12” sewer main installed
26.5/28 sewer laterals installed
11/11 sewer manholes installed

100% Residential Lots

For Residential Properties

Start Date: 05 JAN 24
Completion Date:
11 SEP 24

Total Lots: 1390
Lots Cleared: 1390
Lots Complete: 1390

100% Commercial Lots

For Commercial/Public Properties

Start Date: 27 FEB 24
Completion Date:
26 FEB 25

Total Lots: 148
Lots Cleared: 148
Lots Complete: 148
Shoring & Bracing Historical Structures: 6 of 6

Have Questions?

The County of Maui welcomes your questions and feedback to help guide efforts in providing you and the community with the most beneficial information.

Feel free to email support@mauirecovers.com directly.

Mahalo for sharing your comments and feedback. Our team will get back to you shortly.

Oops! Something went wrong while submitting the form.

Have Questions?

The County of Maui welcomes your questions and feedback to help guide efforts in providing you and the community with the most beneficial information.

Feel free to email support@mauirecovers.com directly.

Mahalo for sharing your comments and feedback. Our team will get back to you shortly.

Oops! Something went wrong while submitting the form.